Hybrid power plant for school with heat pumps. 42 kW.

pic
pic
pic
pic
pic
pic
pic

To reduce power consumption at the school, we designed a hybrid project that included a hybrid solar power plant, heat pumps "air-air" and backup power from the battery. In addition to the school itself, we also powered street lighting, which works from a unit of gel battery. Estimated consumption savings range from 70% to 90%. Heat pumps will not only generate heat in winter, autumn and spring, but also cool rooms in the summer.

List of equipment:

  • FEM New-Tek NTE 400-72M - 104 pcs.
  • Hybrid Inverter Afore 30 kW - 1 pcs.
  • Hybrid Inverter Growatt 5 kW - 1 pcs.
  • LFP Leoch battery pack - 28.8 kWh
  • GEL battery pack - 28.8 kWh